Road Work Update 6/16

Bayley Hazen Road from the blacktop to Ewells Mills Road (Ski Tow Road) is now open. That project has been completed.

Since the emergency work has been mostly completed, except for the remaining closed roads, it is our intention to try to complete repairs as quickly as possible. As noted yesterday, there is a lack of available material but the road crew is still working long hours to do everything it can. Completing repairs will consist of fixing the ditches, opening plugged culverts, and laying down a top coat of gravel. The point of trying to complete work on a road is to attempt to prevent future destruction of the work already performed.  We will also be working to get one-lane areas back to two-lanes as soon as we can.

The first finish project will be Old Cemetery Road. That should be finished sometime next week. At the same time, another crew will be working on Macks Mountain Road. That road will take at least another two weeks to complete. After Old Cemetery Road we will move to Green Bay Loop to finish that project. Again that will probably take close to two weeks. Once these roads are done we will post the next roads to be tackled.

This schedule is entirely dependent upon cooperation from Mother Nature. Another weather event or other emergency will mean a new schedule. Let us hope that the crazy weather is over.

No comments:

Post a Comment